Home  |  About Us   |  Contact Us  Site Map   |  FAQs   |  Careers  |  Links 
 
 

Generation Projects
Hoover Uprating
Magnolia Power
San Juan Unit 3 Power
Palo Verde Power
Canyon Power Project

Transmission Projects
Mead-Adelanto Transmission
Mead-Phoenix Transmission
Southern Transmission System

Renewable Energy Projects
Ameresco Landfill Gas-to-Energy Project
Ice Energy Project
Ormat Geothermal Project
MWD Hydropower Project
Tieton Hydropower Project
High Winds Energy Contract
Linden Wind Energy Project
Milford Wind Project
Pebble Springs Wind Project
Southwestern Wyoming Wind Contract
Windy Point Project

Natural Gas
Natural Gas Project - Pinedale
Natural Gas Project - Barnett
Natural Gas Project - Prepaid

 

SCPPA Participants: Anaheim, Azusa, Banning, Burbank, Colton, Riverside

Year Built: 1935
(Generation Uprated: 1983)

Peak Plant Capacity: 1951 MW
(Currently Rated: 1717 MW due to drought)

Future Plans:
Negotiations for contracts expiring in 2017 are already underway.

SCPPA agreed to advance funds for a portion of the uprating of 17 hydroelectric generating units at the Hoover Dam Power Plant in exchange for capacity and energy allocations associated with the uprating.

Generation capacity was increased from 1,488 MW to 1,951 MW.

SCPPA members hold capacity entitlements of an 18.68% in the uprating project.

Paid $27 million to Western Area Power Administration in advance.